Turbine collapse and oil spill reported to have shut Nysäter wind farm
2022Published 3 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on wind (onshore) incidents in Sweden, and an email when EIR-1955 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Nordex
What happened
A July 2022 report says a turbine collapsed at the Nordex-equipped Nysäter wind project in Sweden, and that the collapse and an oil spill shut the site. The project had had a ribbon-cutting by RWE only weeks earlier, and was described as one of Europe's largest and newest wind farms. The cause, the size of the spill, any injuries, and how long the shutdown lasted were not reported.
Contributing factors
Not reported.
Lessons learned
- Early operation after opening is still a period when a turbine failure can shut a whole site, so monitoring should not be relaxed after a ribbon-cutting.
- A collapse can be accompanied by an oil spill that affects the wider site, so containment and notification plans should be in place before operation.
- Neighbouring turbines should be confirmed safe before any restart after a collapse.
More lessons on detection and monitoring, structural integrity and turbines, from every incident on the register.
Published 2026-10-03. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.