Energy sites / United Kingdom / Hereford and Worcester

Solar · United Kingdom

Stockton Court farm

Awaiting Construction5 MWChecked 6 October 2026Last changed in the dataset 17 September 2019

Technology
Solar
Capacity
5 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Renewable Power Exchange
Location
Land Off, Stockton Road, Stockton-on-Teme, Worcester, Hereford and Worcester, WR6 6UT, United Kingdom
Planning authority
Malvern Hills
Planning application
15/01017/FUL
Appeal reference
APP/J1860/W/16/3149836

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 11 August 2015 Planning application submitted
  • 13 April 2016 Planning permission refused
  • 24 June 2016 Appeal lodged
  • 5 April 2017 Planning permission granted
  • 5 April 2017 Appeal granted
  • 1 May 2021 Planning permission expired

None found. The register holds no published incident that names Stockton Court farm. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.