Onshore wind · United Kingdom

St Johns Wells Wind Cluster Extension

Operational3.2 MWChecked 6 October 2026Last changed in the dataset 5 March 2015

Technology
Onshore wind
Capacity
3.2 MW
Status
Operational
Operator or applicant
Green Cat Renewables
Location
St Johns Wells, Fyvie, Turriff AB53 8PX, Grampian, United Kingdom
Planning authority
Aberdeenshire
Planning application
APP/2009/4121
First operating
2015
Turbines
4

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 11 January 2010 Planning application submitted
  • 22 June 2012 Planning permission granted
  • 30 October 2013 Construction started
  • 1 March 2015 Operational

None found. The register holds no published incident that names St Johns Wells Wind Cluster Extension. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.