Solar farm at land at The Willows, Uttoxeter

Operational6.4 MWChecked 6 October 2026Last changed in the dataset 20 April 2017

Technology
Solar
Capacity
6.4 MW
Status
Operational
Operator or applicant
TGC Renewables
Location
Land South East Of The Willows, Dove Walk, Uttoxeter, Staffordshire, Staffordshire, ST14 8EJ, United Kingdom
Planning authority
East Staffordshire
Planning application
P/2015/00434
First operating
2017

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 April 2015 Planning application submitted
  • 24 July 2015 Planning permission granted
  • 12 December 2016 Construction started
  • 31 March 2017 Operational

None found. The register holds no published incident that names Solar farm at land at The Willows, Uttoxeter. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.