← Back to Highland

Energy sites / United Kingdom / Highland

Onshore wind · United Kingdom

Millennium Extension

Operational10 MWChecked 6 October 2026Last changed in the dataset 10 May 2016

Technology
Onshore wind
Capacity
10 MW
Status
Operational
Operator or applicant
West Coast Energy /Falck Renewables
Location
Millennium Windfarm on The Achlain and Invergarry amd Aberchalder Estates Glengarry Invergarry Inverness-Shire, Highland, United Kingdom
Planning authority
Highland
First operating
2008
Turbines
4, 125 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 10 March 2007 Planning application submitted
  • 12 January 2008 Planning permission granted
  • 13 January 2008 Construction started
  • 1 December 2008 Operational

None found. The register holds no published incident that names Millennium Extension. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.