Millennium Extension II

Operational15 MWChecked 6 October 2026Last changed in the dataset 5 May 2011

Technology
Onshore wind
Capacity
15 MW
Status
Operational
Operator or applicant
West Coast Energy Ltd/Falck Renewables
Location
Millennium Windfarm, on The Achlain and Invergarry amd Aberchalder Estates, Glengarry Invergarry, Inverness-Shire, (nr Glen Moriston, Fort Augustus), Highland, United Kingdom
Planning authority
Scottish Government (S36)
First operating
2011
Turbines
6

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 6 January 2009 Planning application submitted
  • 10 August 2009 Planning permission granted
  • 1 April 2010 Construction started
  • 1 April 2011 Operational

None found. The register holds no published incident that names Millennium Extension II. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.