← Back to Highland

Energy sites / United Kingdom / Highland

Onshore wind · United Kingdom

Tomchrasky Estate Wind farm

Awaiting Construction84 MWChecked 6 October 2026Last changed in the dataset 1 July 2025

Technology
Onshore wind
Capacity
84 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
E Power Limited
Location
900m Ne/O Beinn An T-Sidhein Dalchreichart, Highland, IV3, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00004663
Turbines
14, 185 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 November 2022 Planning application submitted
  • 6 May 2025 Planning permission granted
  • 6 May 2028 Planning permission expired

None found. The register holds no published incident that names Tomchrasky Estate Wind farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.