← Back to Ayrshire
Planning pack for this site, £295Other options

Onshore wind · United Kingdom

Knockcronal Wind Farm

Operator Statkraft UK Limited · Owner Ministry Of Trade, Industry And Fisheries

Awaiting Construction59.4 MWData checked 16 November 2026Source record dated 8 January 2026

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Knockcronal Wind Farm is a 59.4 MW wind farm 20 km east of Girvan, Ayrshire, United Kingdom. Its planning application (ECU00002181) went to Scottish Government (S36) on 17 November 2021 and was granted on 5 November 2025. Its status in the Renewable Energy Planning Database (UK government) is awaiting construction. There are 18 other energy sites within 10 km, 8 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

STATKRAFT UK LTD (05742795), active, since 2006. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Knockcronal Wind Farm sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0922, Vestas turbine nacelle fire at Ardrossan wind farm during storm, 25 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-09222011Vestas turbine nacelle fire at Ardrossan wind farm during storm25 kmSignificant
EIR-11342017Wind turbine tower collapses at Kilgallioch Wind Farm, Ayrshire25 kmSignificant
EIR-10252018Worker dies after becoming stranded at Afton wind farm31 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Onshore wind
Capacity
59.4 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Statkraft UK Limited
Owner
Ministry Of Trade, Industry And Fisheries
Location
4.8 km south of Straiton and 17.4 km east of Girvan, Maybole, Ayrshire, KA19 7NF, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00002181
Turbines
9, 200 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for ECU00002181, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 17 November 2021 Planning application submitted
  • 5 November 2025 Planning permission granted
  • 5 November 2030 Planning permission runs out

None found. The register holds no published incident that names Knockcronal Wind Farm. If you know of one, report it (confidential reports are anonymised).

Has Knockcronal Wind Farm had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Knockcronal Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Knockcronal Wind Farm?
Awaiting Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 8 January 2026.
Where is Knockcronal Wind Farm?
20 km east of Girvan, Ayrshire, United Kingdom (postcode KA19 7NF).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).