Soay Solar Farm and Greener Grid Park

Under Construction200 MWChecked 6 October 2026Last changed in the dataset 6 March 2026

Technology
Battery storage (Co-located with RE)
Capacity
200 MW
Status
Under Construction
Operator or applicant
Statkraft Uk Limited
Location
Three Cocked Hat Plantation, Waplington Lane, Allerthorpe, York, North Yorkshire, YO42 4RL, United Kingdom
Planning authority
East Riding of Yorkshire
Planning application
21/04505/STPLF

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 26 January 2022 Planning application submitted
  • 28 November 2022 Planning permission granted
  • 1 September 2025 Construction started
  • 28 November 2025 Planning permission expired

None found. The register holds no published incident that names Soay Solar Farm and Greener Grid Park. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.