← Back to Highland

Onshore wind · United Kingdom

Hill of Lybster (Wind Turbine - Extension)

Operator The Energy Workshop

Operational1.5 MWData checked 16 November 2026Source record dated 2 October 2018

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Hill of Lybster (Wind Turbine - Extension) is a 1.5 MW wind farm 9 km west of Thurso, Highland, United Kingdom. Its planning application (17/04934/FUL) went to Highland on 20 October 2017 and was granted on 16 August 2018. It has been operating since 12 April 2021. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 27 other energy sites within 10 km, 16 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 3 other sites and 132 energy sites within 40 km for Hill of Lybster (Wind Turbine - Extension)

Members see the sites and incidents around this one, and every record behind them.

THE ENERGY WORKSHOP LIMITED (04546615), active, since 2002. 1 outstanding charge on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
1.5 MW (this record)
All phases
6.4 MW, the phases on the register added up
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
The Energy Workshop
Location
Land 200M N Of, 3 Lybster Road, Forss, Thurso, Highlands, Highland, KW14 7YA, United Kingdom
Planning authority
Highland
Planning application
17/04934/FUL
First operating
2021
Turbines
1, 100 m to tip

This record is 1.5 MW, one part of a site built in phases. With Hill of Lybster (4.9 MW) the phases on the register add up to 6.4 MW. Hill of Lybster

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 17/04934/FUL, with what the planning evidence pack adds for this site.

Every application in Highland · Alerts for applications and incidents near here

  • 20 October 2017 Planning application submitted
  • 16 August 2018 Planning permission granted
  • 12 April 2021 Operational

None found. The register holds no published incident that names Hill of Lybster (Wind Turbine - Extension). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Hill of Lybster (Wind Turbine - Extension) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Hill of Lybster (Wind Turbine - Extension); it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Hill of Lybster (Wind Turbine - Extension)?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 2 October 2018.
Where is Hill of Lybster (Wind Turbine - Extension)?
9 km west of Thurso, Highland, United Kingdom (postcode KW14 7YA).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).