Forss Wind Farm (Extension)

Operational5.2 MWChecked 6 October 2026Last changed in the dataset 10 May 2016

Technology
Onshore wind
Capacity
5.2 MW
Status
Operational
Operator or applicant
Renewable Energy Systems (RES)
Location
Ex Navy Base Forss, Dounreay Thurso Caithness, Highland, KW14 7YB, United Kingdom
Planning authority
Highland
Planning application
01/00380/FULCA
First operating
2007
Turbines
4

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 5 January 2005 Planning application submitted
  • 16 October 2006 Planning permission granted
  • 1 January 2007 Construction started
  • 1 July 2007 Operational

None found. The register holds no published incident that names Forss Wind Farm (Extension). If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.