Hill of Easterton
Operator Mackies
Operational2.5 MWData checked 16 November 2026Source record dated 1 October 2009
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Hill of Easterton is a 2.5 MW wind farm 10 km north of Inverurie, Grampian, United Kingdom. Its planning application went to Aberdeenshire on 15 June 2011 and was granted on 16 October 2003. It has been operating since 1 January 2005. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 34 other energy sites within 10 km, 22 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Hill of Easterton changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 2.5 MW (this record)
- All phases
- 4.5 MW, the phases on the register added up
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Mackies
- Location
- Hill of Easterton, 1km North Of Mackies Ice Cream Dairy, Westertown, Rothienorman, Inverurie, AB51 8US, Grampian, United Kingdom
- Planning authority
- Aberdeenshire
- First operating
- 2005
- Turbines
- 1
This record is 2.5 MW, one part of a site built in phases. With Hill of Easterton Extension (2 MW) the phases on the register add up to 4.5 MW. Hill of Easterton Extension
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page, with what the planning evidence pack adds for this site.
Every application in Aberdeenshire · Alerts for applications and incidents near here
Timeline
- 16 October 2003 Planning permission granted
- 1 January 2005 Operational
- 15 June 2011 Planning application submitted
Incidents on the register at this site
None found. The register holds no published incident that names Hill of Easterton. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Hill of Easterton had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Hill of Easterton; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Hill of Easterton?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 1 October 2009.
- Where is Hill of Easterton?
- 10 km north of Inverurie, Grampian, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).