Onshore wind · United Kingdom

Druim Leathann

Revised49.7 MWChecked 6 October 2026Last changed in the dataset 28 May 2020

Technology
Onshore wind
Capacity
49.7 MW
Status
Revised
Operator or applicant
BayWa r.e. (formerly Forsa)
Location
Druim Leathann Windfarm North, Lochside, North Tolsta, Isle Of Lewis, Western Isles, HS2 0NF, United Kingdom
Planning authority
Na h-Eileanan Siar
Planning application
17/00282/PPDM
Turbines
14, 127 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 2 June 2017 Planning application submitted
  • 16 February 2023 Planning permission expired

None found. The register holds no published incident that names Druim Leathann. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.