← Back to Borders

Energy sites / United Kingdom / Borders

Onshore wind · United Kingdom

Crystal Rig Wind Farm Phase IV

Under Construction48 MWChecked 6 October 2026Last changed in the dataset 3 February 2024

Technology
Onshore wind
Capacity
48 MW
Status
Under Construction
Operator or applicant
Fred Olsen Renewables
Location
Crystal Rigg Wind Farm Cranshaws Duns Scottish Borders, Borders, TD11 3SR, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00000607
Appeal reference
WIN-140-8
Turbines
11, 200 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 30 May 2018 Planning application submitted
  • 4 July 2019 Appeal lodged
  • 24 March 2021 Planning permission granted
  • 24 March 2021 Appeal granted
  • 1 August 2024 Construction started
  • 24 March 2027 Planning permission expired

None found. The register holds no published incident that names Crystal Rig Wind Farm Phase IV. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.