Crystal Rig Wind Farm Phase IV

Operator Fred Olsen Renewables · Owner Fred. Olsen Renewables UK Holdings As

Under Construction48 MWData checked 16 November 2026Source record dated 3 February 2024

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Crystal Rig Wind Farm Phase IV is a 48 MW wind farm 11 km south of Dunbar, Borders, United Kingdom. Its planning application (ECU00000607) went to Scottish Government (S36) on 30 May 2018 and was granted on appeal on 24 March 2021. Construction started on 1 August 2024. Its status in the Renewable Energy Planning Database (UK government) is under construction. There are 29 other energy sites within 10 km, 14 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

FRED. OLSEN RENEWABLES LIMITED (13633932), active, since 2021. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack for Crystal Rig Wind Farm Phase IV sets out every comparable incident for this project, with sources. £295, by email in minutes; the order form arrives filled in from this record.

Get the evidence pack for this site, £295 See a sample pack (PDF)

The pack for this site lists 49 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-0441, Wind turbine collapses at Aviva's Pitheavlis site in Perth, 78 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-04412025Wind turbine collapses at Aviva's Pitheavlis site in Perth78 kmSignificant
EIR-13862022Wind turbine fire near St Cyrus in Aberdeenshire97 kmMinor
EIR-09112017Worker dies after fall from turbine at Whitelee windfarm near Glasgow111 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 46 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack
Technology
Onshore wind
Capacity
48 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Under Construction
Operator or applicant
Fred Olsen Renewables
Owner
Fred. Olsen Renewables UK Holdings As
Location
Crystal Rigg Wind Farm Cranshaws Duns Scottish Borders, Borders, TD11 3SR, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00000607
Appeal reference
WIN-140-8
Turbines
11, 200 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for ECU00000607, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 30 May 2018 Planning application submitted
  • 4 July 2019 Appeal lodged
  • 24 March 2021 Planning permission granted
  • 24 March 2021 Appeal granted
  • 1 August 2024 Construction started

None found. The register holds no published incident that names Crystal Rig Wind Farm Phase IV. If you know of one, report it (confidential reports are anonymised).

Has Crystal Rig Wind Farm Phase IV had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Crystal Rig Wind Farm Phase IV; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Crystal Rig Wind Farm Phase IV?
Under Construction, in the Renewable Energy Planning Database (UK government), where it last changed on 3 February 2024.
Where is Crystal Rig Wind Farm Phase IV?
11 km south of Dunbar, Borders, United Kingdom (postcode TD11 3SR).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).