Onshore wind · United Kingdom
Clashindarroch 2
Awaiting Construction77 MWChecked 6 October 2026Last changed in the dataset 28 June 2023
The site
- Technology
- Onshore wind
- Capacity
- 77 MW
- Status
- Awaiting Construction (Appeal Granted)
- Operator or applicant
- Vattenfall
- Location
- Clashindarroch Forest, Huntly, Grampian, United Kingdom
- Planning authority
- Scottish Government (S36)
- Planning application
- ECU00002002
- Appeal reference
- WIN-110-2
- Turbines
- 14, 180 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 23 December 2019 Planning application submitted
- 10 February 2021 Planning permission refused
- 10 May 2021 Appeal lodged
- 26 June 2023 Appeal granted
- 11 August 2023 Planning permission granted
- 26 June 2028 Planning permission expired
Incidents on the register at this site
None found. The register holds no published incident that names Clashindarroch 2. If you know of one, report it (confidential reports are anonymised).
Follow Clashindarroch 2
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.