← Back to Moray

Energy sites / United Kingdom / Moray

Battery storage · United Kingdom

Clashindarroch Wind Farm Extension

Awaiting Construction50 MWChecked 6 October 2026Last changed in the dataset 8 January 2026

Technology
Battery storage (Co-located with RE)
Capacity
50 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Infinergy
Location
Cabrach Estate, approximately 8km south east of Dufftown, 9km south west of Huntly, and 7.5km north west of Rhynie, Moray, AB54 4QS, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
ECU00004695

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 13 January 2023 Planning application submitted
  • 18 December 2025 Planning permission granted
  • 18 December 2030 Planning permission expired

None found. The register holds no published incident that names Clashindarroch Wind Farm Extension. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 177 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.