Solar · United Kingdom

Chittering Solar Farm Extension

Operator Abbey Properties Cambs

Operational6.3 MWData checked 16 November 2026Source record dated 12 April 2013

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Chittering Solar Farm Extension is a 6.3 MW solar farm 5.8 km north of Waterbeach, Cambridgeshire, United Kingdom. Its planning application (S/1542/12/FL) went to South Cambridgeshire on 24 July 2012 and was granted on 15 October 2012. It has been operating since 21 March 2013. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 37 other energy sites within 10 km, 22 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

313 energy sites within 40 km for Chittering Solar Farm Extension

Members see the sites and incidents around this one, and every record behind them.

Technology
Solar
Capacity
6.3 MW (this record)
All phases
11.3 MW, the phases on the register added up
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Abbey Properties Cambs
Location
Land at, Radical Farm, Chittering Drove, Chittering, Cambridgeshire, Cambridgeshire, United Kingdom
Planning authority
South Cambridgeshire
Planning application
S/1542/12/FL
First operating
2013

This record is 6.3 MW, one part of a site built in phases. With Chittering Solar Farm (5 MW) the phases on the register add up to 11.3 MW. Chittering Solar Farm

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for S/1542/12/FL, with what the planning evidence pack adds for this site.

Every application in South Cambridgeshire · Alerts for applications and incidents near here

  • 24 July 2012 Planning application submitted
  • 15 October 2012 Planning permission granted
  • 28 January 2013 Construction started
  • 21 March 2013 Operational

None found. The register holds no published incident that names Chittering Solar Farm Extension. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Chittering Solar Farm Extension had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Chittering Solar Farm Extension; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of Chittering Solar Farm Extension?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 12 April 2013.
Where is Chittering Solar Farm Extension?
5.8 km north of Waterbeach, Cambridgeshire, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).