Abergorki Wind Farm

Awaiting Construction13.5 MWChecked 6 October 2026Last changed in the dataset 4 November 2024

Technology
Onshore wind
Capacity
13.5 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
Thrive Renewables
Location
Craig yr Aber, Land North-East of Ffoch-orky, Treorchy, Rhondda Cynon Taf, Mid Glamorgan, CF42 6TF, United Kingdom
Planning authority
Rhondda Cynon Taf
Planning application
13/0663/10
Turbines
3, 149.9 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 27 June 2013 Planning application submitted
  • 23 July 2015 Planning permission granted
  • 23 July 2018 Planning permission expired

None found. The register holds no published incident that names Abergorki Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.