Full planning pack, launch price £145Other options

Planning application · Solar · Redcar and Cleveland

Yearby Village - Tees Solar Farm

Awaiting Construction49.9 MWApplication R/2023/0002/FFMSubmitted 3 January 2023Granted 30 April 2024

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
R/2023/0002/FFM
Planning authority
Redcar and Cleveland
County or area
Cleveland
Nation
England
Technology
Solar
Capacity
49.9 MW
Status
Awaiting Construction (Planning Permission Granted)
Operator or applicant
EDF Energy Renewables
Location
Near Yearby Village, South Of Redcar, Yearby, Redcar, TS10 4SG
  • 3 January 2023 Planning application submitted
  • 30 April 2024 Planning permission granted
  • 30 April 2027 Planning permission expired Date as recorded in the register

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1502, Storm Eowyn damages solar panels at Newton Aycliffe Leisure Centre, 32 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-15022025Storm Eowyn damages solar panels at Newton Aycliffe Leisure Centre32 kmMinor
EIR-11752026Rooftop solar panel fire guts NHS mental health ward in Malton53 kmSignificant
EIR-14992025Solar panels linked to fires at council buildings in Northumberland65 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near TS10 4SG is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Redcar and Cleveland.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.