← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Maldon

Turncole Wind Farm

Operational17.5 MWApplication 10/01070/FULSubmitted 30 June 2011Granted on appeal 14 February 2014

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
10/01070/FUL
Planning authority
Maldon
County or area
Essex
Nation
England
Technology
Onshore wind
Capacity
17.5 MW
Status
Operational
Operator or applicant
RES/ Aviva
Location
Turncole Farm, The Marshes, Southminster, Essex, CM0 7JJ
Appeal reference
APP/X1545/A/12/2174982
Turbines
7
First operating
2016
  • 30 June 2011 Planning application submitted
  • 25 October 2011 Planning permission refused
  • 14 February 2014 Planning permission granted
  • 14 February 2014 Appeal granted
  • 31 October 2015 Construction started
  • 22 December 2016 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1275, Fire damages Siemens Gamesa turbine at French Farm wind farm, 102 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-12752022Fire damages Siemens Gamesa turbine at French Farm wind farm102 kmSignificant
EIR-15782024Wind turbine fire near Chumleigh in Devon102 kmSignificant
EIR-08952018Wind turbine catches fire at Doddington wind farm after storms109 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near CM0 7JJ is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Maldon.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.