Onshore wind · United Kingdom
Turncole Wind Farm
Operator RES& Aviva
Operational17.5 MWData checked 16 November 2026Source record dated 22 December 2016
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Turncole Wind Farm is a 17.5 MW wind farm 4.2 km north-east of Burnham-on-Crouch, Essex, United Kingdom. Its planning application (10/01070/FUL) went to Maldon on 30 June 2011 and was granted on appeal on 14 February 2014. It has been operating since 22 December 2016. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 12 other energy sites within 10 km, 4 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Turncole Wind Farm changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 17.5 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- RES& Aviva
- Location
- Turncole Farm, The Marshes, Southminster, Essex, Essex, CM0 7JJ, United Kingdom
- Planning authority
- Maldon
- Planning application
- 10/01070/FUL
- Appeal reference
- APP/X1545/A/12/2174982
- First operating
- 2016
- Turbines
- 7
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for 10/01070/FUL, with what the planning evidence pack adds for this site.
Every application in Maldon · Alerts for applications and incidents near here
Timeline
- 30 June 2011 Planning application submitted
- 25 October 2011 Planning permission refused
- 14 February 2014 Planning permission granted
- 14 February 2014 Appeal granted
- 31 October 2015 Construction started
- 22 December 2016 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Turncole Wind Farm. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Turncole Wind Farm had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Turncole Wind Farm; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Turncole Wind Farm?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 22 December 2016.
- Where is Turncole Wind Farm?
- 4.2 km north-east of Burnham-on-Crouch, Essex, United Kingdom (postcode CM0 7JJ).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).