← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · East Renfrewshire

NEILSTON WIND FARM

Operational9.2 MWApplication 2009/0744/TPSubmitted 19 November 2009Granted 16 May 2011

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
2009/0744/TP
Planning authority
East Renfrewshire
County or area
Strathclyde
Nation
Scotland
Technology
Onshore wind
Capacity
9.2 MW
Status
Operational
Operator or applicant
Renewables Infrastructure Group
Location
N/w Of Nether Carswell Farm, Drumgrain Tip, Kingston Road, Neilston, Glasgow, Strathclyde, G44
Turbines
4
First operating
2013
  • 19 November 2009 Planning application submitted
  • 16 May 2011 Planning permission granted
  • 1 March 2012 Construction started
  • 13 May 2013 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1157, Fire destroys turbine at Whitelee windfarm near Glasgow, 6.6 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-11572026Fire destroys turbine at Whitelee windfarm near Glasgow6.6 kmSignificant
EIR-09112017Worker dies after fall from turbine at Whitelee windfarm near Glasgow12 kmMajor
EIR-19512022Investigation begins after turbine fire at Ardrossan wind farm25 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near NEILSTON WIND FARM is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in East Renfrewshire.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.