Nether Carswell Cottage Wind Turbine

Awaiting Construction4.2 MWChecked 6 October 2026Last changed in the dataset 10 July 2025

Technology
Onshore wind
Capacity
4.2 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Nether Carswell Three Limited
Location
370m S/O Nether Carswell Cottage Kingston Road, Neilston Kilmarnock, Strathclyde, KA3 4EQ, United Kingdom
Planning authority
East Ayrshire
Planning application
2020/0578/TP
Appeal reference
APPEAL 0559
Turbines
1, 124.75 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 25 September 2020 Planning application submitted
  • 3 April 2024 Planning permission refused
  • 10 May 2024 Appeal lodged
  • 10 May 2025 Planning permission granted
  • 10 May 2025 Appeal granted
  • 10 May 2028 Planning permission expired

None found. The register holds no published incident that names Nether Carswell Cottage Wind Turbine. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.