← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Solar · Cornwall

Menear Road - Solar & Battery storage

Awaiting Construction17.5 MWApplication PA23/09532Submitted 5 March 2024Granted on appeal 13 February 2026

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
PA23/09532
Planning authority
Cornwall
Nation
England
Technology
Solar
Capacity
17.5 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Anesco Limited
Location
E/O Menear Farm Menear Road St Austell, PL25 3JT
  • 5 March 2024 Planning application submitted
  • 23 April 2025 Planning permission refused
  • 4 November 2025 Appeal lodged
  • 13 February 2026 Planning permission granted
  • 13 February 2026 Appeal granted
  • 13 February 2031 Planning permission expired Date as recorded in the register

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1528, Fire at solar farm conversion unit in Roche extinguished, 7.5 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-15282023Fire at solar farm conversion unit in Roche extinguished7.5 kmMinor
EIR-15412015Transformer unit fire at a solar farm on Copshorn Road, Bodmin13 kmMinor
EIR-15442014Fire at solar panel installation near Bodmin Jail13 kmMinor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near PL25 3JT is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Cornwall.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.