← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Solar · Perth and Kinross

Coupar Angus Substation, Pleasance Road - Solar Farm

Application Refused49.9 MWApplication 23/01294/FLMSubmitted 18 August 2023Refused 14 December 2023

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
23/01294/FLM
Planning authority
Perth and Kinross
County or area
Tayside
Nation
Scotland
Technology
Solar
Capacity
49.9 MW
Status
Application Refused (Planning Permission Refused)
Operator or applicant
Coupar Two Limited
Location
Se/O Coupar Angus Substation, Pleasance Road, Coupar Angus, Blairgowrie, PH13 9AA
  • 18 August 2023 Planning application submitted
  • 14 December 2023 Planning permission refused

The pack for this site lists 89 comparable solar incidents in the United Kingdom, nearest first. The nearest is EIR-1476, House fire reported to have started on solar panels in Carnoustie, 34 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-14762026House fire reported to have started on solar panels in Carnoustie34 kmSignificant
EIR-12382019Leak from solar heating system at Carnegie Leisure Centre Dunfermline53 kmMinor
EIR-20162022Solar panel fire evacuates Hawick High School127 kmSignificant
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 86 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near PH13 9AA is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Perth and Kinross.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.