← Back to the applications
Full planning pack, launch price £145Other options

Planning application · Onshore wind · Northumberland

Blyth Harbour Wind Farm (re-power)

Operational3.4 MWApplication 07/00287/FULESSubmitted 6 July 2007Granted 21 July 2008

In the evidence packHidden: in the evidence packnearest refused scheme •• kmShown in the pack
Application number
07/00287/FULES
Planning authority
Northumberland
Nation
England
Technology
Onshore wind
Capacity
3.4 MW
Status
Operational
Operator or applicant
Hainsford Energy
Location
Blyth Harbour, North Blyth, Cambois, Bedlington, Northumberland
Turbines
1
First operating
2012
  • 6 July 2007 Planning application submitted
  • 21 July 2008 Planning permission granted
  • 1 June 2011 Construction started
  • 1 September 2012 Operational

The pack for this site lists 43 comparable onshore wind incidents in the United Kingdom, nearest first. The nearest is EIR-1119, Wind turbine fire at Butterwick Wind Farm near Sedgefield, 53 km from this site.

ReferenceYearIncidentFrom the siteSeverity
EIR-11192019Wind turbine fire at Butterwick Wind Farm near Sedgefield53 kmMinor
EIR-08632017Fire destroys single turbine at Knabs Ridge wind farm near Harrogate126 kmSignificant
EIR-16242026Crane topples on Scout Moor wind farm project157 kmMajor
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••
••••••••••••••••••••••••••••••••••••••••••••••••••••

The first 3 rows as the pack shows them. The other 40 are in the pack, each with its distance, sources and the fire service guidance it bears on.

The map

Summary for this site

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

Paragraphs for the planning statement

This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack. This part of the pack is written for this site and opens with the pack.

In the full pack

Alerts for applications near here

An email when another battery, solar or wind application near Blyth Harbour Wind Farm (re-power) is added or decided, or an incident is recorded nearby. Free, nothing else, one click to stop.

By signing up you agree to the privacy policy. UK planning data is from the government's planning database, updated monthly.

Want to see a pack first? Download a sample pack (PDF). It is an example pack for a 50 MW battery project in Lincolnshire, with every section and the first rows of each table.

The site's own page has its map, the energy sites around it and anyone can follow it for changes. Every planning application. Every application in Northumberland.

Data updated 3 August 2026 from the Renewable Energy Planning Database (DESNZ), published quarterly.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.