NorNed cable out of service after fire at Eemshaven converter station
Apr 2009Published 17 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the Netherlands, and an email when EIR-2926 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): TenneT
What happened
On Saturday 11 April 2009 the NorNed cable, a 700 MW high-voltage link carrying electricity from Norway to the Netherlands, was taken out of operation after a fire at the Eemshaven converter station in the Netherlands. According to a press release from TenneT, the Dutch transmission system operator, dated 15 April 2009, no interruption in electricity supply occurred when the cable was disconnected. TenneT said transmission was not expected to be possible for several weeks at least.
A later press release stated that the cable would return to operation from 16 May 2009. The outage reduced supply on the Dutch market and raised electricity prices for Dutch consumers, while Norwegian households and companies benefited from lower prices at home. The source describes the disruption as an economically critical event.
Contributing factors
Not reported. The source identifies a fire at the Eemshaven converter station but does not give its cause.
Lessons learned
- Fire damage to converter equipment can keep a high-voltage interconnector out of service for weeks, so operators should plan for long repair lead times and hold contingency arrangements.
- Interconnector outages move prices across borders, so transmission operators should communicate expected restoration dates early and update them as repairs progress.
- A single cable link leaves both connected markets exposed to one point of failure, so operators and planners should weigh redundancy against the economic cost of outages.
More lessons on electrical protection and isolation, from every incident on the register.
Source
Other entries that name Eemshaven
Published 2026-11-17. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.