NorNed subsea interconnector cable fault takes link out of service
May 2022Published 18 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the Netherlands, and an email when EIR-2953 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): TenneT and Statnett
What happened
On 6 May 2022 the NorNed cable, which links Norway and the Netherlands, went out of service due to a fault. Investigations located the fault in the Dutch section of the cable, near the coast. Repair work was carried out during the summer months. The repair was complex because of the specific type of cable and the position of the fault, and it required special equipment. The investigation into the failure then found that another, small section of the cable, apart from the repaired section, was in a more degraded state than expected, which increased the risk of future cable failure.
Replacement of about 1.3 kilometres of the cable connection was said to be likely necessary to secure the lifetime of the cable. Return to operation was postponed until 17 October, and TenneT and Statnett were assessing interim measures to operate the link as well as possible during the winter months.
Contributing factors
The source does not state the cause of the fault. Cable experts were investigating what had caused the reduced condition of the degraded section. The repair was complicated by the cable type and the coastal position of the fault. Storm season from October to April prevents work on the cable, and a new section of cable had to be produced.
Lessons learned
- Faults near a coastal landing point may need specialised equipment, so operators should plan repair capability and access in advance.
- After a repair, condition checks of neighbouring cable sections can reveal wider degradation, so adjacent sections should be tested rather than only the repaired part.
- Seasonal weather windows can block subsea cable work for months, so long-lead replacement cable should be ordered early to shorten the outage.
More lessons on spacing, layout and fire spread, weather and external hazards, from every incident on the register.
Source
Published 2026-11-18. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.