Grid infrastructureNetherlandsEIR-2953

NorNed subsea interconnector cable fault takes link out of service

May 2022Published 18 Nov 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersMedium confidence
supply cut for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): TenneT and Statnett

On 6 May 2022 the NorNed cable, which links Norway and the Netherlands, went out of service due to a fault. Investigations located the fault in the Dutch section of the cable, near the coast. Repair work was carried out during the summer months. The repair was complex because of the specific type of cable and the position of the fault, and it required special equipment. The investigation into the failure then found that another, small section of the cable, apart from the repaired section, was in a more degraded state than expected, which increased the risk of future cable failure.

Replacement of about 1.3 kilometres of the cable connection was said to be likely necessary to secure the lifetime of the cable. Return to operation was postponed until 17 October, and TenneT and Statnett were assessing interim measures to operate the link as well as possible during the winter months.

The source does not state the cause of the fault. Cable experts were investigating what had caused the reduced condition of the degraded section. The repair was complicated by the cable type and the coastal position of the fault. Storm season from October to April prevents work on the cable, and a new section of cable had to be produced.

  1. Faults near a coastal landing point may need specialised equipment, so operators should plan repair capability and access in advance.
  2. After a repair, condition checks of neighbouring cable sections can reveal wider degradation, so adjacent sections should be tested rather than only the repaired part.
  3. Seasonal weather windows can block subsea cable work for months, so long-lead replacement cable should be ordered early to shorten the outage.

More lessons on spacing, layout and fire spread, weather and external hazards, from every incident on the register.

Published 2026-11-18. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Grid infrastructure incidents in the Netherlands, by year, free with a credit (PNG).

Grid infrastructure incidents in the Netherlands: 20 entries, with a free alert for the next one.

See power line and cable failures.

Browse the full register or submit an incident.