V.C. Summer nuclear plant offline after brief transformer fire
Nov 2021Published 18 Nov 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-2954 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
What happened
The V.C. Summer nuclear plant in Fairfield County, South Carolina, was taken offline at about 5:30 p.m. on a Monday, shortly before the report of 17 November 2021, after a failure of its main step-up transformer, which sends power from the station onto the grid. The failure caused a brief fire, which the plant's fire system put out quickly. On 16 November at about 9:00 a.m., a sheen of transformer mineral oil was seen in the station's circulating water outfall.
Station personnel deployed absorbent booms and oil screens to contain and clean up the oil, and an estimated 10 to 15 gallons leaked. Officials said there was no impact on the health and safety of the public or plant personnel. The cause of the transformer failure was unknown and an investigation was under way at the time of reporting.
Contributing factors
The cause of the transformer failure was unknown and under investigation at the time of reporting. The mineral oil leak was seen in the station's circulating water outfall.
Lessons learned
- Fire suppression systems on large transformers should be tested and ready to act, as the rapid activation here limited the fire.
- Oil containment such as absorbent booms and oil screens should be staged at water outfalls so that a transformer leak can be stopped before it reaches the water.
- The cause of a transformer failure should be established before the equipment is returned to service, and findings should be shared with operators of similar units.
More lessons on fire suppression and firefighting, from every incident on the register.
Source
Published 2026-11-18. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.