Transformer explosion and fire at Entergy substation in Port Neches
Apr 2020Published 8 Oct 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in the United States, and an email when EIR-2149 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Entergy
What happened
At about 8 p.m. on Tuesday 28 April 2020, a transformer at an Entergy-managed substation in the distribution yard of the petrochemical plant in Port Neches, Texas, exploded and caught fire. Indorama Ventures, which had recently acquired the Huntsman plant, reported the incident. The substation supplies power to Port Neches, Groves and parts of the plant. Indorama's onsite fire brigade and the Port Neches Fire Department responded shortly after the explosion, and Entergy crews attended.
Indorama reported no injuries and no detected releases. Power outages within the plant took some units offline. Entergy said the transformer had failed and that the cause was still under investigation, and that crews had isolated the issue and restored all customers. Indorama said plant units were back online or restarting and that there had been no off-site impacts from the plant during the outage or recovery. Entergy crews were also responding to severe weather that night, which left around 20,000 people without power across Southeast Texas; the source does not link that weather to this failure.
Contributing factors
The source does not state a cause. Entergy said the transformer failed and that the source of the failure was still under investigation. Severe weather was affecting the wider network that night, but the source does not link it to the failure.
Lessons learned
- Substations that feed industrial sites need fire separation and rapid isolation so that a transformer failure does not spread or cut power to neighbouring communities.
- Plants with an onsite fire brigade should agree response arrangements with the utility and the local fire department in advance.
- Operators should plan for sudden loss of supply, with safe shutdown and restart sequences for each unit, so that units can be restarted once power is restored.
More lessons on spacing, layout and fire spread, fire suppression and firefighting, outages, backup supply and restoration, from every incident on the register.
Source
Other entries that name Entergy
- Fire at Entergy power station followed by power restoration
- Fire at Entergy substation closed La. 70 in St. James Parish, Louisiana
- Fire at Entergy Mississippi substation followed by power restoration
- Fire at Entergy Substation on Dieu Street in Port Neches
- Transformer fire at Entergy substation causes major outage in Louisiana
Published 2026-10-08. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.