Grid infrastructureMaltaEIR-2140

Vessel anchor reported to have damaged the Malta-Italy subsea interconnector, later repaired by Nexans and Enemalta

2022Published 8 Oct 2026Responsible editor: Chief Editor

Estimated damageEstimated by the register's adjusterHow? Know the real figure?
Figure hidden: shown to subscribersHigh confidence
supply cut for about •• daysShown in the record →Full estimate
From the recordRoot cause hiddenFailed part hidden

Companies named in the reporting of this entry (being named is not a finding of fault): Enemalta, Nexans

A December 2022 report says the 98-kilometre Malta-Italy subsea interconnector, which links Malta to the European electricity grid in Sicily, was damaged in a storm by a vessel anchor in March. Enemalta has said electricity from the interconnector forms around 20 per cent of Malta's electricity mix. The cable was switched off during the repair, and supply came from local sources, including Enemalta's plants. Enemalta engineers and technicians worked with Nexans at sea in Qalet Marku and Baħar iċ-Ċagħaq over about three weeks before early December 2022.

A replacement section stored at Delimara power station was loaded in October onto the cable-laying vessel Nexans Aurora. A robot was reported to have cut out more than 1.5 km of damaged cable; cast iron protective shells were removed and the damaged part was replaced. Nexans confirmed that the repair works were finalised. The source says testing was completed so the link could be re-energised, but it does not state that it had been re-energised.

Enemalta said it had opened a legal case for damages against the owners of the vessel Chem P. The repairs alone were reported to cost around EUR 25 million.

The source states that the cable was damaged in a storm by a vessel anchor. It does not say whether the vessel was in an authorised anchorage, or whether the cable route was marked or otherwise protected.

  1. Third-party contact, including anchoring, can take a subsea interconnector out of service, so operators need a way to cover demand from other sources while the link is off.
  2. Spare cable and access to a cable-laying vessel can shorten replacement of a damaged section.
  3. Repair costs and the identity of the vessel involved should be recorded from the start if a claim for damages is to be pursued.

More lessons on electrical protection and isolation, from every incident on the register.

Published 2026-10-08. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.

See the register's stories first in Google: add it as a preferred source.

Chart to reuse with this story: Grid infrastructure incidents in Malta, by year, free with a credit (PNG).

Grid infrastructure incidents in Malta: 9 entries, with a free alert for the next one.

See power line and cable failures.

Browse the full register or submit an incident.