Transformer fire at Pattabhiram substation prompts replacement
2024Published 29 Sept 2026Responsible editor: Chief Editor
Get the next one by email
Free alerts on grid infrastructure incidents in India, and an email when EIR-1607 is updated. No account needed; unsubscribe in one click.
Confirm your email and every substation and transformer incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Tamil Nadu Generation, Tangedco
What happened
One of three 16 MVA power transformers at the Pattabhiram substation was damaged by fire on a Saturday, causing a night-long power cut in the locality. Tamil Nadu Generation and Distribution Corporation commissioned a replacement transformer on the following Tuesday. Minor power disruptions were still being reported after commissioning. A Tangedco official said that, normally, it takes time for the entire load to shift to a newly installed transformer.
Contributing factors
The source does not report the cause of the fire.
Lessons learned
- A multi-transformer substation can restore supply by replacing a damaged unit, but customers may still see short disruptions while load is transferred.
- Spare transformer arrangements and a rehearsed installation plan shorten outages at urban substations.
- After a replacement is energised, operators should monitor the load transfer and tell customers that minor disruptions may continue.