Vestas V150 turbine collapses at Aldermyrberget wind farm in Sweden
2020Published 17 Sept 2026Responsible editor: Chief Editor
- Where
- Aldermyrberget wind farm in Sweden
- Owner
- Wpd
- Manufacturer
- Vestas
- What
- Vestas V150 4.2MW turbine collapsed
- Injuries
- None reported
Get the next one by email
Free alerts on wind (onshore) incidents in Sweden, and an email when EIR-1011 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): Vestas
What happened
A Vestas V150 4.2MW wind turbine collapsed in November 2020 at the Aldermyrberget wind farm in Sweden, owned by Wpd, while the site was ramping up towards full commissioning. Nobody was hurt in the incident. A subsequent investigation identified a bonding failure on the turbine's blade-root inserts, caused by a manufacturing issue at a single supplier, which allowed a blade to become loose and destabilise the turbine before it fell.
As a precaution, Vestas then took around 150 V150 turbines that could potentially be exposed to the same fault out of service while it worked on a repair or replacement solution with affected customers. The company said no other operational turbines had been affected and that the fault was unrelated to two earlier V150 blade incidents reported in the United States and Australia.
Contributing factors
A bonding failure on blade-root inserts, attributed by Vestas to a manufacturing issue at a single component supplier, allowed a blade to loosen and destabilise the turbine.
Lessons learned
- A manufacturing defect in blade-root inserts can loosen a blade and destabilise the turbine, so operators must verify supplier quality controls on critical structural parts.
- A fault found in one turbine of a new platform requires checks on the whole batch before commissioning, so owners should apply structural integrity tests to units still in ramp-up.
- A single supplier fault can affect many turbines, so owners and insurers should demand batch-level traceability for blade inserts and similar components.
More lessons on structural integrity and turbines, from every incident on the register.
Not yet known
- Turbine exact age and service hours
- Duration of site downtime
- Cost of repairs and lost output
This entry is updated when these are reported. Get an alert for the next one like it.
Site page: Aldermyrberget wind farm (status, dates and other incidents)