Storm reported to have damaged panels at Bhadla Solar Park in Rajasthan
Apr 2019Published 17 Sept 2026Responsible editor: Chief Editor
- Where
- Bhadla Solar Park, Bhadla, Jodhpur district, Rajasthan
- What
- Storm damaged large number of solar panels
- Cause
- Wind speeds as high as 130 km per hour
Get the next one by email
Free alerts on solar PV incidents in India, and an email when EIR-1004 is updated. No account needed; unsubscribe in one click.
Confirm your email and every solar incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
What happened
On 17 April 2019 a storm was reported to have struck Bhadla Solar Park in Bhadla, Jodhpur district, Rajasthan. Saur Energy reported that wind speeds as high as 130 km per hour were recorded at the site and that a large number of solar panels were damaged. At the time the park was reported to have an existing installed capacity of more than 1500 MW. The same storm was reported to have caused wider damage across several states. Developers named at the park include Acme, SB Energy, Azure Energy, Adani Energy and Renew Power. Which of those companies' assets were damaged was not reported.
Contributing factors
Wind speeds as high as 130 km per hour were reported at the site. An unnamed EPC contractor told the source that local sandstorms were allowed for in design, and suggested that undulating terrain or small construction variances can be amplified in extreme winds. That view has not been independently confirmed.
Lessons learned
- Mounting and foundation designs at solar parks must be checked against recorded extreme wind events of 130 km per hour rather than only typical local conditions.
- Large solar parks should assess how undulating terrain or small construction variances can increase wind loads on panels.
More lessons on structural integrity and turbines, from every incident on the register.
Not yet known
- Which developers' assets were damaged
- Exact number of panels damaged
- Age and model of the solar panels
- Cost of damage and downtime
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Site page: Bhadla solar farm (status, dates and other incidents)
Other entries that name Rajasthan
Published 2026-09-17. Written from public reporting. Descriptive, not investigative. See the data accuracy disclaimer.