Wind turbine blade shatters and falls at Sumac Ridge wind farm in Ontario
Apr 2019Published 17 Sept 2026Responsible editor: Chief Editor
- Where
- Sumac Ridge wind farm west of Bethany, Ontario
- Owner
- WPD Wind
- What
- Turbine blade bent, partially shattered and fell
- Cause
- Under investigation
Get the next one by email
Free alerts on wind (onshore) incidents in Canada, and an email when EIR-1003 is updated. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Companies named in the reporting of this entry (being named is not a finding of fault): WPD Wind
What happened
On a Saturday morning in April 2019, residents near Pontypool in the City of Kawartha Lakes, Ontario, reported hearing a loud screeching noise from a wind turbine. One of the turbine's blades, reported to weigh about 5,400 kilograms and measure 45 metres long, was found bent and had partially shattered, with sections of the blade falling to the ground. The turbine is one of five on the Sumac Ridge site west of Bethany, which had been operating for about three years at the time.
The site owner, WPD Wind, said such damage was rare and confirmed it would investigate the cause. No cause had been determined at the time of reporting, and officials were still investigating the extent of the damage.
Contributing factors
Not reported. The operator stated it had no comment on a possible cause and would launch an investigation.
Lessons learned
- A 45 metre blade weighing 5,400 kilograms can shed large sections, so operators must maintain exclusion zones and inspect blades on all turbines of the same model.
- A loud screeching noise reported by residents can indicate imminent blade failure, so operators should investigate such reports at once.
More lessons on structural integrity and turbines, from every incident on the register.
Not yet known
- Turbine model and age
- Exact cause of the blade failure
- Cost of damage and downtime
- Extent of debris and repairs needed
This entry is updated when these are reported. Get an alert for the next one like it.
Source
Site page: Sumac Ridge wind farm (status, dates and other incidents)