← Back to West Midlands

Energy sites / United Kingdom / West Midlands

Solar · United Kingdom

Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels

Under Construction25 MWChecked 6 October 2026Last changed in the dataset 11 September 2025

Technology
Solar
Capacity
25 MW
Status
Under Construction
Operator or applicant
Novus Renewable Services Limited
Location
Tolldish Hall Farm Parrotts Grove, Coventry, West Midlands, CV2 1NR, United Kingdom
Planning authority
Rugby
Planning application
39235

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 17 October 2022 Planning application submitted
  • 31 August 2023 Planning permission granted
  • 1 April 2024 Construction started

None found. The register holds no published incident that names Tolldish Hall Farm, Parrotts Grove - Solar Photovoltaic Panels. If you know of one, report it (confidential reports are anonymised).

The register holds 86 incidents at solar farms in the United Kingdom, 59 of them fires, and 344 worldwide. Counts of incidents in published reporting, not rates.

What fails at solar farms · All solar farms incidents

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.