Battery storage · United Kingdom

Coventry National Grid Substation

Operational49.9 MWChecked 6 October 2026Last changed in the dataset 25 July 2025

Technology
Battery storage (Stand-alone Storage)
Capacity
49.9 MW
Status
Operational
Operator or applicant
Pivot Power
Location
National Grid Substation, Parrotts Grove, Coventry, West Midlands, West Midlands, CV2 1NQ, United Kingdom
Planning authority
Coventry
Planning application
FUL/2020/1476
First operating
2023

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 2 July 2020 Planning application submitted
  • 22 January 2021 Planning permission granted
  • 1 July 2022 Construction started
  • 1 December 2023 Operational

None found. The register holds no published incident that names Coventry National Grid Substation. If you know of one, report it (confidential reports are anonymised).

The register holds 14 incidents at battery storage sites in the United Kingdom, 9 of them fires, and 176 worldwide. Counts of incidents in published reporting, not rates.

What fails at battery storage sites · All battery storage incidents

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.