Operator Lumicity

Appeal Refused11 MWData checked 16 November 2026Source record dated 4 May 2016

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

The Engine Shed Field is a 11 MW solar farm 5.3 km south-west of Deal, Kent, United Kingdom. Its planning application (13/01106) went to Dover on 24 December 2013 and was refused on appeal on 29 April 2016. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 24 other energy sites within 10 km, 17 of them solar farms (hybrid battery and solar sites included). The register holds no incident at this site. It holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom, and 480 worldwide.

The operator's 10 other sites and 175 energy sites within 40 km for The Engine Shed Field

Members see the sites and incidents around this one, and every record behind them.

LUMICITY LTD (07324912), active, since 2010. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Solar
Capacity
11 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Appeal Refused
Operator or applicant
Lumicity
Location
Old Engine Shed Field, Sutton Court Farm, (Land between Pineham & East Langdon), Kent, United Kingdom
Planning authority
Dover
Planning application
13/01106
Appeal reference
APP/X2220/W/15/3138584

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for 13/01106, with what the planning evidence pack adds for this site.

Every application in Dover · Alerts for applications and incidents near here

  • 24 December 2013 Planning application submitted
  • 18 September 2015 Planning permission refused
  • 9 December 2015 Appeal lodged
  • 29 April 2016 Appeal refused

None found. The register holds no published incident that names The Engine Shed Field. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has The Engine Shed Field had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names The Engine Shed Field; it holds 104 incidents at solar farms (hybrid battery and solar sites included) in the United Kingdom.
What is the status of The Engine Shed Field?
Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 4 May 2016.
Where is The Engine Shed Field?
5.3 km south-west of Deal, Kent, United Kingdom.