Onshore wind · United Kingdom

Slieveglass

Operational6.9 MWChecked 6 October 2026Last changed in the dataset 27 November 2018

Technology
Onshore wind
Capacity
6.9 MW
Status
Operational
Operator or applicant
Slieveglass wind farm (Energia)
Location
Bullock Park, Drumquin, Co. Tyrone, Co. Tyrone, United Kingdom
Planning authority
Fermanagh and Omagh
Planning application
J/2008/0088
Appeal reference
2012/A0053
First operating
2018
Turbines
3

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 28 January 2008 Planning application submitted
  • 30 April 2012 Planning permission refused
  • 12 June 2013 Planning permission granted
  • 12 June 2013 Appeal granted
  • 1 September 2017 Construction started
  • 10 August 2018 Operational

None found. The register holds no published incident that names Slieveglass. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.