Onshore wind · United Kingdom
Lough Hill
Operator B9 & Renewable Energy Systems (RES)
Operational10.5 MWData checked 16 November 2026Source record dated 10 May 2016
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Lough Hill is a 10.5 MW wind farm 16 km north-west of Dromore, Co. Tyrone, United Kingdom. Its planning application (K/2004/1139/F) went to Derry City and Strabane on 1 July 2004 and was granted on 23 December 2005. It has been operating since 1 August 2006. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 25 other energy sites within 10 km, 22 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Lough Hill changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 10.5 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- B9 & Renewable Energy Systems (RES)
- Location
- Lough HillEast of DrumquinCounty Tyrone, Co. Tyrone, United Kingdom
- Planning authority
- Derry City and Strabane
- Planning application
- K/2004/1139/F
- First operating
- 2006
- Turbines
- 6
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for K/2004/1139/F, with what the planning evidence pack adds for this site.
Every application in Derry City and Strabane · Alerts for applications and incidents near here
Timeline
- 1 July 2004 Planning application submitted
- 23 December 2005 Planning permission granted
- 1 February 2006 Construction started
- 1 August 2006 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Lough Hill. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Lough Hill had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Lough Hill; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Lough Hill?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 10 May 2016.
- Where is Lough Hill?
- 16 km north-west of Dromore, Co. Tyrone, United Kingdom.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).