Onshore wind · United Kingdom
Shepham Lane
Operational7.5 MWChecked 6 October 2026Last changed in the dataset 1 May 2018
The site
- Technology
- Onshore wind
- Capacity
- 7.5 MW
- Status
- Operational
- Operator or applicant
- Foresight
- Location
- Land off Shepham Lane, North of A27, Polegate, East Sussex, BN24 5BT, United Kingdom
- Planning authority
- Wealden
- Planning application
- WD/2013/0346/MEA
- Appeal reference
- APP/C1435/A/13/2208526
- First operating
- 2017
- Turbines
- 3
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 18 February 2013 Planning application submitted
- 9 May 2013 Planning permission refused
- 18 December 2013 Appeal lodged
- 7 January 2015 Planning permission granted
- 7 January 2015 Appeal granted
- 16 August 2016 Construction started
- 12 January 2017 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Shepham Lane. If you know of one, report it (confidential reports are anonymised).
Follow Shepham Lane
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.