Meall Buidhe Wind Farm

Awaiting Construction40 MWChecked 6 October 2026Last changed in the dataset 19 May 2026

Technology
Onshore wind
Capacity
40 MW
Status
Awaiting Construction (Appeal Granted)
Operator or applicant
Muirden Energy
Location
Land 4420M NW Of, Croick Estate, Ardgay, Highlands, Highland, IV24 3BW, United Kingdom
Planning authority
Highland
Planning application
20/02659/FUL
Appeal reference
22/00046/REFSU
Turbines
8, 150 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 21 August 2020 Planning application submitted
  • 27 July 2022 Planning permission refused
  • 20 October 2022 Appeal lodged
  • 14 June 2023 Planning permission granted
  • 14 June 2023 Appeal granted
  • 14 June 2026 Planning permission expired

None found. The register holds no published incident that names Meall Buidhe Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Preparing, reviewing or responding to a planning application for a site like this? The planning evidence pack sets out every comparable incident for one project, with sources. £295, by email in minutes.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.