Marston Vale Country Park Wind Turbine

Operator Blue Energy

Operational1.5 MWData checked 16 November 2026Source record dated 20 January 2015

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Marston Vale Country Park Wind Turbine is a 1.5 MW wind farm 3.7 km south-west of Kempston Hardwick, Bedfordshire, United Kingdom. Its planning application (CB/11/04077/FULL) went to Central Bedfordshire on 11 November 2011 and was granted on 1 February 2012. It has been operating since 1 May 2014. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 46 other energy sites within 10 km, one of them a wind farm. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 6 other sites and 603 energy sites within 40 km for Marston Vale Country Park Wind Turbine

Members see the sites and incidents around this one, and every record behind them.

BLUE ENERGY LIMITED (06456350), active, since 2007. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
1.5 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Blue Energy
Location
The Marston Vale Millennium Country Park, Station Road, Marston Moretaine, Bedford, MK43 0PR, Bedfordshire, United Kingdom
Planning authority
Central Bedfordshire
Planning application
CB/11/04077/FULL
First operating
2014
Turbines
1

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for CB/11/04077/FULL, with what the planning evidence pack adds for this site.

Every application in Central Bedfordshire · Alerts for applications and incidents near here

  • 11 November 2011 Planning application submitted
  • 1 February 2012 Planning permission granted
  • 23 October 2013 Construction started
  • 1 May 2014 Operational

None found. The register holds no published incident that names Marston Vale Country Park Wind Turbine. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Marston Vale Country Park Wind Turbine had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Marston Vale Country Park Wind Turbine; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Marston Vale Country Park Wind Turbine?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 20 January 2015.
Where is Marston Vale Country Park Wind Turbine?
3.7 km south-west of Kempston Hardwick, Bedfordshire, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).