Onshore wind · United Kingdom
Lochend Wind Farm
Operational9.2 MWChecked 6 October 2026Last changed in the dataset 19 May 2017
The site
- Technology
- Onshore wind
- Capacity
- 9.2 MW
- Status
- Operational
- Operator or applicant
- Wind Harvest
- Location
- Land 978M SE Of 2 Lochend Holding Barrock, Highland, United Kingdom
- Planning authority
- Highland
- Planning application
- 13/02682/FUL
- Appeal reference
- PPA-270-2108
- First operating
- 2017
- Turbines
- 4
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 29 July 2013 Planning application submitted
- 31 March 2014 Planning permission refused
- 27 June 2014 Appeal lodged
- 11 December 2014 Planning permission granted
- 11 December 2014 Appeal granted
- 15 May 2016 Construction started
- 15 May 2017 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Lochend Wind Farm. If you know of one, report it (confidential reports are anonymised).
Follow Lochend Wind Farm
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.