Lochend Wind Farm

Operational9.2 MWChecked 6 October 2026Last changed in the dataset 19 May 2017

Technology
Onshore wind
Capacity
9.2 MW
Status
Operational
Operator or applicant
Wind Harvest
Location
Land 978M SE Of 2 Lochend Holding Barrock, Highland, United Kingdom
Planning authority
Highland
Planning application
13/02682/FUL
Appeal reference
PPA-270-2108
First operating
2017
Turbines
4

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 29 July 2013 Planning application submitted
  • 31 March 2014 Planning permission refused
  • 27 June 2014 Appeal lodged
  • 11 December 2014 Planning permission granted
  • 11 December 2014 Appeal granted
  • 15 May 2016 Construction started
  • 15 May 2017 Operational

None found. The register holds no published incident that names Lochend Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.