← Back to Strathclyde

Onshore wind · United Kingdom

Kype Muir Wind Farm Extension

Operator Banks Renewables · Owner Onpath Energy Limited

Operational67.2 MWData checked 16 November 2026Source record dated 4 November 2024

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Kype Muir Wind Farm Extension is a 67.2 MW wind farm 5.3 km south of Strathaven, Strathclyde, United Kingdom. Its planning application (EC00002083) went to Scottish Government (S36) on 10 October 2014 and was granted on 16 September 2016. It has been operating since 1 October 2024. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 36 other energy sites within 10 km, 32 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 26 other sites and 525 energy sites within 40 km for Kype Muir Wind Farm Extension

Members see the sites and incidents around this one, and every record behind them.

BANKS RENEWABLES (BOWBURN SOLAR PARK) LIMITED (13062412), active, since 2020. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
67.2 MW (this record)
All phases
156 MW, the phases on the register added up
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Operational
Operator or applicant
Banks Renewables
Owner
Onpath Energy Limited
Location
approximately 5 km south of the town of Strathaven, Strathclyde, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
EC00002083
First operating
2024
Turbines
15, 200 m to tip

This record is 67.2 MW, one part of a site built in phases. With Kype Muir Wind Farm (88.4 MW) the phases on the register add up to 156 MW. Kype Muir Wind Farm

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for EC00002083, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 10 October 2014 Planning application submitted
  • 16 September 2016 Planning permission granted
  • 1 June 2021 Construction started
  • 1 October 2024 Operational

None found. The register holds no published incident that names Kype Muir Wind Farm Extension. If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Kype Muir Wind Farm Extension had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Kype Muir Wind Farm Extension; it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Kype Muir Wind Farm Extension?
Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 4 November 2024.
Where is Kype Muir Wind Farm Extension?
5.3 km south of Strathaven, Strathclyde, United Kingdom.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).