Onshore wind · United Kingdom

Gayton Le Marsh Wind Farm

Operational16.4 MWChecked 6 October 2026Last changed in the dataset 4 March 2016

Technology
Onshore wind
Capacity
16.4 MW
Status
Operational
Operator or applicant
Energiekontor UK
Location
Carlton Grange, Thacker Bank, Great Carlton, Gayton Le Marsh, Louth, Lincolnshire (3.3km to the northeast of Great Carlton and 2.4km south of Saltfleetby), Lincolnshire, LN11 7TXL, United Kingdom
Planning authority
East Lindsey
Planning application
N/063/01392/11
Appeal reference
APP/D2510/A/12/2176754/NWF
First operating
2016
Turbines
8

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

  • 15 August 2011 Planning application submitted
  • 25 May 2012 Planning permission refused
  • 5 April 2013 Planning permission granted
  • 5 April 2013 Appeal granted
  • 17 February 2015 Construction started
  • 26 February 2016 Operational

None found. The register holds no published incident that names Gayton Le Marsh Wind Farm. If you know of one, report it (confidential reports are anonymised).

The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.

What fails at onshore wind farms

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.