Onshore wind · United Kingdom
Garreg Lwyd
Operator Renewables Infrastructure Group (TRIG)
Operational34 MWData checked 16 November 2026Source record dated 4 October 2017
Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.
Garreg Lwyd is a 34 MW wind farm 12 km south of Newtown, Powys, United Kingdom. Its planning application (P/2008/0785) went to Powys on 27 May 2008 and was granted on appeal on 14 May 2015. It has been operating since 22 February 2017. Its status in the Renewable Energy Planning Database (UK government) is operational. There are 7 other energy sites within 10 km, 5 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.
Get an email when Garreg Lwyd changes
Free. An email when its status changes: a planning decision, building starting, going live or closing. And each Monday, onshore wind incidents in the United Kingdom. No account needed; unsubscribe in one click.
Confirm your email and every wind turbine incident on the register arrives at once as a spreadsheet (CSV), free.
Get a free sample brief Three complete verified records and the incidents-per-GW table, by email within a minute.
We will also email you about the register's paid records and plans, at most once a week and three times in all. You can stop these at any time. By signing up you agree to the privacy policy.
Members see the sites and incidents around this one, and every record behind them.
The site
- Technology
- Onshore wind
- Capacity
- 34 MW
- Capacity figure from
- Renewable Energy Planning Database (UK government)
- Status
- Operational
- Operator or applicant
- Renewables Infrastructure Group (TRIG)
- Location
- Garreg Lwyd Hill Between Felindre & Llanbadarn Fynydd, Llandrindod Wells, Powys, Powys, LD1 6YF, United Kingdom
- Planning authority
- Powys
- Planning application
- P/2008/0785
- Appeal reference
- APP/T6850/A/13/2209593
- First operating
- 2017
- Turbines
- 17, 137 m to tip
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
The planning application page for P/2008/0785, with what the planning evidence pack adds for this site.
Every application in Powys · Alerts for applications and incidents near here
Timeline
- 27 May 2008 Planning application submitted
- 5 September 2013 Planning permission refused
- 4 March 2014 Appeal lodged
- 14 May 2015 Planning permission granted
- 14 May 2015 Appeal granted
- 11 January 2016 Construction started
- 22 February 2017 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Garreg Lwyd. If you know of one, report it (confidential reports are anonymised).
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Questions
- Has Garreg Lwyd had a fire or other incident?
- None is on the register as of 21 November 2026. The register holds no published incident that names Garreg Lwyd; it holds 63 incidents at wind farms in the United Kingdom.
- What is the status of Garreg Lwyd?
- Operational, in the Renewable Energy Planning Database (UK government), where it last changed on 4 October 2017.
- Where is Garreg Lwyd?
- 12 km south of Newtown, Powys, United Kingdom (postcode LD1 6YF).
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).