Onshore wind · United Kingdom
Fox Covert Wind Farm
Application Refused10 MWChecked 6 October 2026Last changed in the dataset 27 June 2016
The site
- Technology
- Onshore wind
- Capacity
- 10 MW
- Status
- Application Refused (Secretary of State - Refusal)
- Operator or applicant
- Wind Prospect Developments
- Location
- Cotham Road, Hawton, Nottinghamshire, Nottinghamshire, United Kingdom
- Planning authority
- Newark and Sherwood
- Planning application
- 13/00889/FULM
- Appeal reference
- APP/B3030/W/15/3003130
- Turbines
- 5
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 4 July 2013 Planning application submitted
- 9 October 2014 Planning permission refused
- 10 May 2015 Appeal lodged
- 29 September 2015 Appeal refused
- 20 January 2016 Secretary of State intervened
- 30 June 2016 Refused by the Secretary of State
Incidents on the register at this site
None found. The register holds no published incident that names Fox Covert Wind Farm. If you know of one, report it (confidential reports are anonymised).
Follow Fox Covert Wind Farm
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.