← Back to Borders

Onshore wind · United Kingdom

Fallago Rig 2 (extension)

Operator EDF Energy Renewables

Appeal Refused41 MWData checked 16 November 2026Source record dated 9 July 2020

Watch this siteIts outage notices and incidents, in your workspace and by email. 7 days free, no card.

Fallago Rig 2 (extension) is a 41 MW wind farm 21 km south of Dunbar, Borders, United Kingdom. Its planning application (EC00003102) went to Scottish Government (S36) on 29 January 2016 and was refused on appeal on 25 June 2020. Its status in the Renewable Energy Planning Database (UK government) is appeal refused. There are 11 other energy sites within 10 km, 8 of them wind farms. The register holds no incident at this site. It holds 63 incidents at wind farms in the United Kingdom, and 362 worldwide.

The operator's 59 other sites and 139 energy sites within 40 km for Fallago Rig 2 (extension)

Members see the sites and incidents around this one, and every record behind them.

EDF ENERGY RENEWABLES LIMITED (06456689), active, since 2007. No outstanding charges on the register. Members see the charges register: each charge, when it was created and the lender it is in favour of.

Source: Companies House, matched by the operator's name. If this is the wrong company, tell the editor.

Technology
Onshore wind
Capacity
41 MW
Capacity figure from
Renewable Energy Planning Database (UK government)
Status
Appeal Refused
Operator or applicant
EDF Energy Renewables
Location
Fallago Rig 2, Longformacus, Duns, Borders, TD11 3PB, United Kingdom
Planning authority
Scottish Government (S36)
Planning application
EC00003102
Appeal reference
WIN-140-5
Turbines
12, 127 m to tip

View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.

The planning application page for EC00003102, with what the planning evidence pack adds for this site.

Every application in Scottish Government (S36) · Alerts for applications and incidents near here

  • 29 January 2016 Planning application submitted
  • 21 December 2016 Appeal lodged
  • 25 June 2020 Planning permission refused
  • 25 June 2020 Appeal refused

None found. The register holds no published incident that names Fallago Rig 2 (extension). If you know of one, report it (confidential reports are anonymised).

Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.

Has Fallago Rig 2 (extension) had a fire or other incident?
None is on the register as of 21 November 2026. The register holds no published incident that names Fallago Rig 2 (extension); it holds 63 incidents at wind farms in the United Kingdom.
What is the status of Fallago Rig 2 (extension)?
Appeal Refused, in the Renewable Energy Planning Database (UK government), where it last changed on 9 July 2020.
Where is Fallago Rig 2 (extension)?
21 km south of Dunbar, Borders, United Kingdom (postcode TD11 3PB).

Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts. Nearest town: GeoNames (CC BY 4.0).