Onshore wind · United Kingdom
Carsington Pasture
Operational8 MWChecked 6 October 2026Last changed in the dataset 16 September 2014
The site
- Technology
- Onshore wind
- Capacity
- 8 MW
- Status
- Operational
- Operator or applicant
- Carsington Wind Energy Limited
- Location
- Carsington Pasture, Derbyshire Dales, Derbyshire, United Kingdom
- Planning authority
- Derbyshire Dales
- Planning application
- 07/00083/FUL
- Appeal reference
- 07/00015/INQUIR
- First operating
- 2014
- Turbines
- 4
View on OpenStreetMap. The larger dot is this site; the others are sites within 40 km.
Timeline
- 29 January 2007 Planning application submitted
- 20 July 2007 Planning permission refused
- 17 September 2008 Planning permission granted
- 17 September 2008 Appeal granted
- 15 May 2012 Construction started
- 5 February 2014 Operational
Incidents on the register at this site
None found. The register holds no published incident that names Carsington Pasture. If you know of one, report it (confidential reports are anonymised).
Follow Carsington Pasture
Get one email when this site's status changes in the Renewable Energy Planning Database (UK government), or when the register publishes an incident that names it. Free, no account needed, unsubscribe in one click.
By following you agree to the privacy policy.
Incidents at onshore wind farms in the United Kingdom
The register holds 54 incidents at onshore wind farms in the United Kingdom, 22 of them fires, and 297 worldwide. Counts of incidents in published reporting, not rates.
Own, insure or lend to this site or others like it? A portfolio safety record checks every site in a list against the register, free; the paid records add the site, operator, cause, downtime and loss behind each incident.
Contains public sector information licensed under the Open Government Licence v3.0 (Renewable Energy Planning Database, Department for Energy Security and Net Zero). The dataset. The register adds only the incidents and the counts.